Capítulo 12 de 13 · Section 13 · Clauses 13.1–13.12 · Tables 13.6, 13.6.2.1, 13.6.2.2 · Appendix I (NZ)

Inspection, testing and correction – the CC3 inspection regime

How AS/NZS 5131 Section 13 sets inspection, NDE and correction for CC3 work, and how to build a CC3 ITP an offshore fabricator can deliver.

Every stage needs a documented ITP; at CC3 a full welding ITP is mandatoryRecommended CC3 NDE: 100% visual scan, 20% (SP) or 100% (FP) visual examNDE other than visual by AS ISO 9712 Level 2 personnel (or Level 1 supervised)Coating ITPs are triggered by Coating Quality Level PC2, not by CCEvery inspection record: inspector, item, date, requirement and resultOffshore work relies on hold points, video witness and English records

What Section 13 requires overall

Section 13 is the verification layer of AS/NZS 5131. Clause 13.1 requires that inspection and testing at every stage – procurement, fabrication, surface preparation, painting, galvanizing and erection – follows a documented inspection and test plan (ITP) using documented procedures. Where a quality plan is required (see the quality management chapter), the ITPs sit inside or are attached to it.

The minimum ITP content is the list in Clauses 13.3–13.12, plus anything added by the construction specification and any inspection options selected from Appendix B, Tables B1 and B2. Inspection may be performed by first, second or third parties, and every result, follow-up action and correction must be recorded. Across the section the inspection report has the same five essentials: who inspected, which item, when, against which requirement, and the result.

The designer nominates the construction category and the construction specification governs the project. The extents below are the Standard's minimums or recommendations; refer to the current edition of AS/NZS 5131 for the full requirements.

CC3 ITP reference table

The table below is a practical framework for a CC3 fabrication-and-supply ITP. The witness column shows typical practice, not a requirement of the Standard – the contract decides who attends.

CC3 ITP stages – scope, evidence and typical witnessing (summary in our own words)
Stage (clause)What is inspectedTypical evidenceTypical witness
Incoming materials (13.3)Mill certificates against order and specification, product marking, consumables, bought-in componentsReceiving record, certificate register, heat number logFabricator QC; client document review
Preparation and assembly (13.5)Surface defects before fabrication, identification, cutting, holing, bearing surfaces, assembly checkDimensional and fit-up recordsFabricator QC; client witness of first-off items
Welding (13.6)Before, during and after welding; visual examination and NDEWPS/PQR, welder qualifications, VT and NDE reportsWelding inspector, NDE technician; client hold point
Dimensional (13.4)Member and assembly dimensions against Appendix FMeasurement records, instrument calibrationFabricator QC; client witness
Surface preparation (13.8)Blast grade, profile, treatment gradePre-painting condition reportCoatings inspector; hold before first coat
Painting (13.9)Materials, primer, DFT, continuityDaily inspection reports with batch numbersCoatings inspector; hold after priming
Galvanizing (13.10)Coating to AS/NZS 4680 using the nominated approachGalvanizer certificate, thickness readingsGalvanizer QC; fabricator receiving check
Release and dispatchMarking, completeness, packing, transit protection (Clause 6.11)Release note, packing list, photographsFabricator QC; client pre-shipment inspection
Bolting and erection (13.7, 13.11)Bolt documents, snug-tight and tensioned joints, pre- and post-erection surveyBolt inspection sheets, survey reportErector QC; builder or engineer

Competency of inspection personnel

Each subsection names a competency requirement. The informative notes give benchmarks: for materials, preparation and erection, a relevant trade qualification or standards experience plus more than 10 years in steel fabrication or erection; for surface treatment and paint, a certified coatings inspector (NACE/AMPP or Australasian Corrosion Association) or an equivalent. For welding, Clause 13.6.1.3 is firmer: inspectors must be qualified to the application Standard, and NDE other than visual must be performed by AS ISO 9712 Level 2 personnel, or Level 1 under Level 2 supervision.

Welding inspection and NDE extent by construction category

Full detail is in the welding chapter; the logic in Clause 13.6 is summarised here. NDE extent must be set in the construction specification by weld category and connection.

Welding ITP and recommended NDE by CC (high-level summary of Tables 13.6 and 13.6.2.2(A))
CCWelding ITPRecommended visualRecommended other NDE
CC1Only if triggered*Visual scanning of all weldsNot required
CC2Only if triggered*Full scanning plus 10% examinationSmall UT sample of critical SP butt welds
CC3Mandatory, detailed listFull scanning plus 20% (SP) or 100% (FP) examination10% UT of critical SP butt welds; FP to AS/NZS 1554.4 or .5
CC4Mandatory, detailed listClient specificationClient specification

*Required when the specification calls for it, welding is subcontracted, or an inspection authority or the principal inspects. "Critical" butt welds are those in tension flanges, cruciform joints and restrained joints near plate edges. For Australian structures in earthquake design categories D and E, the greater of Table 13.6.2.2(A) or (B) applies.

  • Ramp-up: inspect the first five connections of a new WPS (or double the specified rate), at least 1.0 m of weld per WPS, then drop to random spot checks while results stay compliant.
  • Escalation: a failed length triggers two further lengths either side; a nonconforming weld triggers root-cause investigation and re-examination.
  • Timing: Table 13.6.2.1 sets minimum hold times before NDE – up to 48 hours for thick, high-heat-input welds in higher-strength steel – and the elapsed time must appear on the NDE report.
  • Sampling: spread across joint types, steel grades, processes and welders; inspect welds before they become inaccessible.

Bolting, coatings, erection and secondary elements

  • Mechanical fastening (13.7): an ITP is required above CC1. Snug-tight joints are checked for bolt position, grade, thread projection and firm ply contact. Tensioned joints at CC2–CC4 are checked by part-turn marks or direct-tension indicators, sampled to ISO 2859-5; no more than 10% of compressible DTIs may be fully compressed. See mechanical fastening.
  • Surface treatment and paint (13.8–13.9): ITPs are required at Coating Quality Level PC2, listing calibrated equipment and sample forms. A pre-painting condition report and inspection after priming are mandatory gates. See corrosion protection.
  • Galvanizing (13.10): inspection follows AS/NZS 4680; variation in hue is not grounds for rejection unless the specification says so.
  • Erection (13.11): pre-erection checks of anchor bolts, levels and grids; post-erection checks of alignment, connections, coatings and grout, plus a survey to the site grid using ISO 7976 methods at a 20°C reference temperature.
  • Secondary elements (13.12): purlins and girts are checked for profile, coating class, laps, bridging, alignment and snug bolts.

Nonconformance and correction

Material lacking adequate documentation is treated as unidentified steel (Clause 13.3.7), which the design Standards take as 170 MPa yield until statistically sound testing proves otherwise. Offcuts returned to stock need their heat number transferred under a documented procedure (Clause 13.3.9). Dimensional nonconformities are corrected and rechecked, or compensated under a written nonconformance procedure (Clause 13.4). Weld defects are repaired to a qualified procedure and re-inspected to the original extent; engineering critical assessment is allowed only if the specification permits it and both principal and fabricator accept it (Clause 13.6.2.5). Defective bolted joints are dismantled, corrected and fully re-inspected (Clause 13.7.7).

Giving the inspector access when the fabricator is offshore

For a fabricator thousands of kilometres from site, the ITP is also the access plan. A workable CC3 arrangement includes:

  • Hold and witness points agreed at ITP approval, with notice periods that allow for travel and NDE hold times.
  • Video witness for fit-up, VT, DFT and dimensional checks, recorded and filed against the piece mark.
  • Pre-shipment inspection before packing is closed, so nonconformances are fixed in the factory, not on site.
  • Records in English, traceable to drawing and piece mark, compiled into a handover dossier.

Independent verification of the system itself – such as World Steel's AS/NZS 5131 CC3 certification and ISO 3834-2 – reduces but never replaces project inspection.

Appendix I – New Zealand only

Appendix I is informative and optional in New Zealand, but becomes binding once specified. It sets weld NDE extent from a failure consequence category (A major, B moderate, C minor) combined with a seismic weld demand level (high, medium, low) tied to member category in NZS 3404 frames. It adds magnetic particle testing of k-areas in heavy hot-rolled sections where cut or welded, mill certificates for tensioned bolts in category A and B joints, and bolt tension verification methods.

Checklist do avaliador

O que um engenheiro, construtor ou auditor deve verificar em um fabricante CC3 para esta parte da AS/NZS 5131 – e as evidências a solicitar.

Cláusula · CCO que verificarEvidências
13.1 CC2–CC4Documented ITP covers every stage, including construction specification and Appendix B options.Approved project ITP within the quality plan
13.3 CC2–CC4Incoming materials and components checked against order, specification and product marking.Receiving inspection records, mill certificate register
13.3.7, 13.3.9 CC1–CC4Undocumented steel is quarantined; offcuts keep their heat identity.Quarantine log, offcut heat-number transfer records
13.5 CC2–CC4Preparation and assembly inspected by a competent person with named inspector and stage.Pre-fabrication surface check, dimensional and assembly records
13.6.1.2 CC3–CC4Welding ITP covers before, during and after welding against the construction specification.Welding ITP listing welds, methods and extents
13.6.1.3 CC1–CC4Weld inspectors qualified; NDE other than visual by Level 2 (or supervised Level 1).Welding inspector qualifications, AS ISO 9712 certificates
13.6.2 CC3NDE extent, timing, sampling and escalation applied as specified.VT and NDE reports with hold time, welder and WPS traceability
13.6.2.5 CC1–CC4Weld defects repaired to qualified procedures and re-inspected to the original extent.NCRs, repair WPS, re-inspection reports
13.8, 13.9 PC2Coating inspections by a competent coatings inspector with mandatory hold gates.Pre-painting condition reports, daily reports, DFT records, calibration
13.4 CC2–CC4Measurement methods, accuracy and frequency defined in the ITP.Calibrated instruments, dimensional reports against Appendix F

Em nossa fábrica

Como a World Steel aplica

01Project ITPs with hold and witness pointsWorld Steel prepares a project ITP for each job, with hold and witness points open to the client's inspector in person or by video.
02Traceability from mill to piece markWorld Steel's quality system links mill certificates for AS/NZS 3678, 3679.1 and 1163 materials to each piece mark, so inspection records can be traced through the job.
03Pre-shipment inspection and dossierWorld Steel applies a pre-shipment inspection before export packing by erection sequence, and issues a Declaration of Compliance and a manufacturer's data report in English.
04Coatings and galvanizing interfacesWorld Steel inspects factory blasting and airless spray painting, and receives hot-dip galvanized items from qualified galvanizers with AS/NZS 4680 documentation.

Perguntas frequentes

Is an ITP mandatory for every AS/NZS 5131 job?

Section 13 requires inspection to a documented ITP at each stage. Several stage-specific ITP clauses exempt CC1, and the welding ITP is only compulsory for CC1 and CC2 when triggered by the specification, subcontracted welding or an inspecting authority. At CC3 and CC4 a detailed welding ITP is always required.