Design deliverables: calculations and drawings

PEB design deliverables explained: approval drawings, anchor bolt plans, design calculations, erection and shop drawings, IFC models and the approval sequence.

Aggiornato 3 min di lettura Visualizza nel modello 3D →

Set of PEB drawings including anchor bolt plan, frame elevations and a 3D IFC model
A PEB project produces a structured set of drawings, calculations and models.

The deliverables chain

A pre-engineered building moves from enquiry to site through a defined sequence of design deliverables. Each one serves a different reader – owner, architect, engineer of record, building authority, foundation contractor, fabricator or erector – and each has a clear approval step. Understanding the set helps buyers review submissions quickly and avoid delays. The typical sequence is:

  1. Design criteria and quotation drawings
  2. Approval (general arrangement) drawings
  3. Anchor bolt plan and reactions
  4. Design calculations (and, where required, sealed submissions)
  5. Erection drawings
  6. Shop (fabrication) drawings and CNC data
  7. 3D model / IFC and as-built records
Diagram of a typical PEB drawing set
Typical PEB drawing set from approval to shop drawings.

What each deliverable contains

Flow chart of the PEB design and build process
Deliverables follow the design-and-build sequence from enquiry to erection.
Main PEB design deliverables
DeliverableContentsUsed by
Approval drawingsPlans, elevations, cross-sections, frame lines, openings, accessories, design loads and codesOwner and architect – to confirm scope and geometry
Anchor bolt planAnchor bolt locations, diameters, projections, base plate sizes, column reactions by load caseFoundation designer and civil contractor
Design calculationsDesign criteria, loads and combinations, frame analysis, member, connection, purlin, girt and bracing checks, deflectionsEngineer of record, checking engineer, authority
Erection drawingsMember marks, frame cross-sections, roof and wall framing plans, bracing, bolt schedules, sheeting and trim layouts, detailsErector and site supervisor
Shop drawingsIndividual part drawings: plate sizes, holes, welds, coatings, piece marksFabrication shop and QC
IFC / 3D modelOpenly exchangeable BIM model of the steel structure for coordination and clash checksDesign team, MEP coordinators, owner
Packing lists and bills of materialPiece lists by container or bundleLogistics and site receiving

Anchor bolt plan first

Foundations are usually built by a local contractor while the steel is in fabrication, so the anchor bolt plan and reactions are issued first, typically immediately after approval drawings are signed. Reactions are given unfactored by load type (dead, collateral, live, snow, wind, seismic, crane) so the foundation designer can apply local combinations. Anchor bolt projections, grout thickness and tolerances must be respected; see base plates and anchor bolts and foundations interface.

Calculations, approvals and local requirements

  • United States and Canada: building permits typically require drawings and calculations sealed by an engineer licensed in the state or province; Canadian projects also need a letter of assurance or similar from the designer.
  • Australia and New Zealand: design certification by a chartered or registered engineer (e.g. CPEng / RPEQ in Queensland) under the National Construction Code or NZ Building Code.
  • Europe: design to Eurocodes with National Annexes; CE marking under EN 1090-1 requires a factory production control route to be arranged per project.
  • Most markets require that the design criteria – codes, loads, deflection limits, materials – be stated on the general notes of the drawings.

Late changes to openings, cranes, mezzanines or loads after approval drawings affect calculations, anchor bolts and fabrication. Freeze scope at the approval stage wherever possible.

Design certification and what the erection set contains

Many authorities and owners ask the PEB supplier for a formal statement that the building was designed for the specified criteria. In North American practice this is a letter of design certification (or letter of assurance in some Canadian provinces) signed by the supplier's engineer, listing the code edition, risk category, roof live, snow, collateral, wind and seismic parameters, crane and mezzanine loads, and the deflection criteria used. In Australia and New Zealand an equivalent design certificate is issued by the registered engineer, and in Europe the design basis is recorded in the declaration documentation for the steel components. The certificate covers the steel package only; foundations, slab and non-supplied items remain with the engineer of record.

Typical contents of a PEB erection drawing set
SheetShows
General notes and design criteriaCodes, loads, materials, coatings, bolt grades and tightening, deflection criteria
Anchor bolt plan and detailsBolt layout, projections, base plate orientation, reactions
Cross-sectionsEach frame type with member marks, splice and connection details
Roof framing planPurlin layout and laps, roof bracing, sag rods, skylights, ventilators
Sidewall and endwall framing elevationsGirts, wall bracing, framed openings, endwall posts
Sheeting and trim layoutsPanel runs, laps, fastener patterns, trims, gutters and downspouts
Standard details and bolt scheduleFlange braces, clips, flashings, bolt sizes and quantities per connection

Each issue carries a revision mark and date; superseded sheets should be withdrawn from site so that erection always follows the current revision.

Erection, shop drawings and IFC at WSC

World Steel produces the full deliverable set in-house: approval drawings, anchor bolt plans, calculations, erection and shop drawings, CNC data for cutting and drilling lines, and IFC models for coordination. The IFC model allows clients and consultants to check clashes with services and view the structure in 3D. Learn more in BIM, IFC and shop drawings, the design-and-build process, and WSC's design service.

Norme per regione

RegioneNormaAmbito
United States MBMA 2018Metal Building Systems Manual – common industry practices
United States AISC 303-22Code of Standard Practice for Steel Buildings and Bridges
Canada CISC Code of Standard PracticeStructural steel documents and responsibilities
Australia / NZ AS/NZS 5131:2016Fabrication and erection – documentation requirements
Europe EN 1090-2Execution of steel structures – execution specification
International ISO 16739-1Industry Foundation Classes (IFC) for data sharing

Domande frequenti

Why is the anchor bolt plan issued before other drawings?

Foundations must be built while steel is fabricated. Issuing anchor bolt layouts and reactions early lets the civil contractor start without waiting for the full drawing set.

Are reactions on the anchor bolt plan factored?

They are normally given unfactored by load type, so the foundation engineer can apply the local code's load combinations.

What is an IFC model used for?

IFC is an open BIM format. It lets architects, MEP engineers and owners view and coordinate the steel model in their own software, check clashes and keep a digital record.

What is a letter of design certification?

It is a signed statement from the PEB supplier's engineer that the steel building has been designed for the listed code, loads and criteria. Authorities and owners often require it with the permit or as-built documents; it does not cover foundations or items not supplied by the PEB manufacturer.