Mezzanine floors

Mezzanine floors in PEBs: column, beam and joist framing, deck options, live loads by code, vibration and deflection, stairs, handrails and installation.

업데이트 4 분 소요 3D 모델에서 보기 →

Steel mezzanine floor with columns, beams, deck and handrails inside a pre-engineered building
A mezzanine adds a second level for offices, storage or plant inside the building.

What a mezzanine floor is

A mezzanine floor is an intermediate floor built inside a building, partly or fully covering the ground floor. In a pre-engineered building it is used for offices above a warehouse, storage platforms, plant and equipment decks, and production levels. The mezzanine consists of columns, main beams, joists, a floor deck, stairs and handrails. It may be tied to the main frame – using the PEB columns for support and lateral stability – or free-standing, with its own bracing. The choice must be made before the main frames are designed, because a tied mezzanine adds vertical and horizontal loads to the frames. See also mezzanine buildings.

Section through a mezzanine floor showing columns, beams, joists and deck
Typical mezzanine section: columns, main beams, joists and composite or plate deck.

Framing and deck options

Mezzanine deck options
Deck typeTypical useNotes
Composite steel deck + concrete slab (about 100–150 mm)Offices, heavy storage, plant roomsFire resistance, good vibration and sound performance
Chequer (tread) platePlant platforms, walkwaysFast to install; noisy; slip resistance depends on pattern
Steel gratingEquipment platforms, ventilated areasLets light, air and sprinkler water pass
Structural particleboard or timber on steel joistsLight storage platformsEconomical; check fire code and moisture

Columns are typically hot-rolled H or hollow sections on their own base plates; main beams are hot-rolled or built-up I-sections; joists are hot-rolled beams or cold-formed C/Z sections, typically spaced 1–3 m depending on the deck.

Joist and deck types in more detail

Joist and deck choices interact: the deck span sets the joist spacing, and the joist type sets the floor depth, the services zone and the fire protection approach.

Mezzanine joist options
Joist typeTypical spanAdvantagesPoints to check
Hot-rolled I-beam4–10 mRobust; easy connections; good for point loads and composite actionWeight; depth for long spans
Cold-formed C or Z joist3–7 mLight, roll-formed with the purlins, bolted cleatsWeb crippling at supports, lateral restraint, vibration
Open-web steel joist6–20 mServices pass through the web; light for long spansDesigned to SJI specifications (US) or CSA S16 joist clauses (Canada); bridging required
Cellular or castellated beam8–18 mLong spans with services through web openingsWeb-post buckling and opening design
Mezzanine deck options in more detail
DeckTypical make-upDesign reference
Composite steel deck with concreteProfiled deck about 0.75–1.2 mm, 50–75 mm deep, with 100–150 mm total slab and meshANSI/SDI C (US), CSA S136 / CSSBI (Canada), AS/NZS 2327 (Australia/NZ), EN 1994-1-1 (Europe)
Non-composite form deckDeck acting as permanent formwork for a reinforced slabSlab designed as reinforced concrete; deck checked for construction loads
Checkered (tread) plateAbout 6–10 mm plate, stiffened at close centresPlate bending and deflection; slip resistance
Steel gratingLoad-bearing bars about 25–50 mm deep, 30–40 mm pitchANSI/NAAMM MBG 531 (US), AS 1657 (Australia), manufacturer load tables
Structural board on joistsParticleboard, plywood or fibre-cement, about 18–25 mmProduct span tables; fire and moisture classification

Where the mezzanine is tied to the main frames, the floor diaphragm (concrete slab or braced deck) can transfer horizontal loads into the PEB columns; a free-standing mezzanine needs its own vertical bracing or moment frames and should be separated from the building frame by a small gap so that the two structures do not interact unintentionally.

Loads and sizing rules

Typical uniform live loads (indicative – confirm with the governing code)
UseASCE 7-22AS/NZS 1170.1EN 1991-1-1
Offices2.4 kPa (50 psf)3.0 kPa2.0–3.0 kPa (cat. B)
Light storage6.0 kPa (125 psf)2.4 kPa per m of storage height7.5 kPa (cat. E1, typical)
Heavy storage12.0 kPa (250 psf)As above, by heightBy assessment
Light manufacturing6.0 kPa (125 psf)Per usePer use
  • Add superimposed dead loads: finishes, ceilings, partitions, services and equipment.
  • Typical deflection limits: span/360 under live load and span/240 under total load (IBC Table 1604.3); tighter limits for brittle finishes.
  • Check floor vibration for walking excitation, especially for offices and long-span light decks (AISC Design Guide 11 or equivalent).
  • Preliminary beam depths of roughly span/18 to span/22 and joist depths of span/20 to span/25 are common starting points.
  • Forklift, pallet-truck or point loads from racking can govern the deck and joists.

Stairs, handrails and fire safety

Stairs, guardrails and handrails must meet the building code of the project location. Typical requirements include guard heights of about 1,070 mm (42 in) under the IBC and NBC, 900–1,100 mm for industrial platforms under AS 1657, and 1,100 mm under EN ISO 14122-3; guards must also resist specified line and point loads. Mezzanines may count toward floor area for fire and egress purposes; codes limit the size of open mezzanines and may require fire-rated construction, sprinklers below and above, and a second escape stair. Coordinate these at concept stage. Stair geometry, ladder fall protection and floor plate options are detailed in staircases, ladders, grating and checkered plate.

Installation and WSC supply

Mezzanine columns are set on base plates anchored to the slab or to separate footings, then beams and joists are bolted using shear-tab or end-plate connections. Deck sheets are fixed to joists, followed by shear studs and slab pour for composite floors. Handrails and stairs are installed last. Tolerances follow the same standards as the main structure – see erection tolerances.

World Steel designs and fabricates complete mezzanine floor systems, including columns, beams, joists, deck, stairs and handrails, integrated with the primary frame and the design loads of the building.

지역별 기준

지역기준범위
United States ASCE 7-22 Ch. 4Live loads, including guard and handrail loads
United States IBC 2021 Sec. 505Mezzanines – area and egress limits
Canada NBC 2020 Part 3 / Part 4Mezzanine fire safety and structural loads
Australia / NZ AS/NZS 1170.1Permanent, imposed and other actions
Australia / NZ AS 1657Fixed platforms, walkways, stairways and ladders
Europe EN 1991-1-1Densities, self-weight and imposed loads
Europe EN ISO 14122-3Permanent means of access – stairs and guard-rails

자주 묻는 질문

Should a mezzanine be tied to the PEB frame or free-standing?

Tying it to the frame can save columns and bracing, but adds load to the main frames. A free-standing mezzanine is independent and easier to modify later. The decision must be made before frame design.

What live load should a storage mezzanine be designed for?

It depends on the code and stored goods: for example ASCE 7-22 gives 125 psf (about 6 kPa) for light storage, while AS/NZS 1170.1 scales storage load with stacking height. Racking point loads must also be checked.

Can a mezzanine be added to an existing steel building?

Yes, usually as a free-standing structure on new footings. If it is to bear on existing columns, the frames and foundations must be checked by an engineer.