Fire protection coating cost – what drives it

Why there is no single price per square metre for intumescent coating, how to calculate litres from area, DFT and volume solids, and the levers that reduce installed cost without reducing fire performance.

World Steel 工程团队 · 更新于 2026-10-16 · 阅读约 2 分钟

Fire protection (illustration)

Cost = litres × price + application + inspection

Material quantity follows directly from area, thickness and volume solids:

Theoretical consumption (L) = Area (m²) × DFT (µm) ÷ (1000 × volume solids fraction). Practical consumption = theoretical ÷ (1 − loss).

Example: 1,000 m² at 1,000 µm DFT with 75 % volume solids needs 1,000 × 1,000 ÷ (1,000 × 0.75) ≈ 1,333 L theoretically; with 25 % application loss about 1,778 L.

The ten cost drivers

  1. Section factor of each member
  2. Fire rating
  3. Critical steel temperature
  4. Surface area
  5. Required DFT
  6. Volume solids of the product
  7. Application losses
  8. Surface preparation and primer
  9. Environment (drying, coats, topcoat)
  10. Inspection requirements

Value engineering levers

  • Use the calculated critical temperature instead of a conservative default.
  • Increase section size where it reduces the section factor of heavily coated members.
  • Compare products – loading tables differ widely.
  • Apply in the shop to reduce losses and site costs.
  • Use boards or sprays where long ratings make coatings uneconomic.

FAQ

How much does intumescent coating cost per m²?

It depends on the DFT, which depends on the member and rating – the same product can cost several times more on a light beam than on a heavy column. Use the estimator with your rates or send the member schedule.

需要您项目的涂层厚度和成本?发送构件清单和耐火等级 – 我们的工程师将编制防火保护方案。
索取方案

Preliminary calculations are provided for estimation purposes only. Final coating thickness and fire protection system selection must be verified against the approved product documentation, applicable project requirements and relevant engineering assessments.

下一个项目

计划在海外建造钢结构?

请发送您的图纸或 IFC 模型——我们的报价团队将回复加工范围、工期及到岸价格。