Fire protection coating cost – what drives it

Why there is no single price per square metre for intumescent coating, how to calculate litres from area, DFT and volume solids, and the levers that reduce installed cost without reducing fire performance.

Đội ngũ kỹ sư World Steel · Cập nhật 2026-10-16 · 2 phút đọc

Fire protection (illustration)

Cost = litres × price + application + inspection

Material quantity follows directly from area, thickness and volume solids:

Theoretical consumption (L) = Area (m²) × DFT (µm) ÷ (1000 × volume solids fraction). Practical consumption = theoretical ÷ (1 − loss).

Example: 1,000 m² at 1,000 µm DFT with 75 % volume solids needs 1,000 × 1,000 ÷ (1,000 × 0.75) ≈ 1,333 L theoretically; with 25 % application loss about 1,778 L.

The ten cost drivers

  1. Section factor of each member
  2. Fire rating
  3. Critical steel temperature
  4. Surface area
  5. Required DFT
  6. Volume solids of the product
  7. Application losses
  8. Surface preparation and primer
  9. Environment (drying, coats, topcoat)
  10. Inspection requirements

Value engineering levers

  • Use the calculated critical temperature instead of a conservative default.
  • Increase section size where it reduces the section factor of heavily coated members.
  • Compare products – loading tables differ widely.
  • Apply in the shop to reduce losses and site costs.
  • Use boards or sprays where long ratings make coatings uneconomic.

FAQ

How much does intumescent coating cost per m²?

It depends on the DFT, which depends on the member and rating – the same product can cost several times more on a light beam than on a heavy column. Use the estimator with your rates or send the member schedule.

Cần độ dày và chi phí cho dự án của bạn?Gửi danh sách cấu kiện và cấp chịu lửa – kỹ sư của chúng tôi lập đề xuất chống cháy.
Yêu cầu đề xuất

Preliminary calculations are provided for estimation purposes only. Final coating thickness and fire protection system selection must be verified against the approved product documentation, applicable project requirements and relevant engineering assessments.

Dự án tiếp theo

Bạn đang lên kế hoạch cho công trình kết cấu thép ở nước ngoài?

Gửi cho chúng tôi bản vẽ hoặc mô hình IFC – bộ phận dự toán sẽ phản hồi phạm vi gia công, tiến độ và giá giao hàng.