Fire protection coating cost – what drives it

Why there is no single price per square metre for intumescent coating, how to calculate litres from area, DFT and volume solids, and the levers that reduce installed cost without reducing fire performance.

World Steel エンジニアリングチーム · 2026-10-16 更新 · 2 分で読めます

Fire protection (illustration)

Cost = litres × price + application + inspection

Material quantity follows directly from area, thickness and volume solids:

Theoretical consumption (L) = Area (m²) × DFT (µm) ÷ (1000 × volume solids fraction). Practical consumption = theoretical ÷ (1 − loss).

Example: 1,000 m² at 1,000 µm DFT with 75 % volume solids needs 1,000 × 1,000 ÷ (1,000 × 0.75) ≈ 1,333 L theoretically; with 25 % application loss about 1,778 L.

The ten cost drivers

  1. Section factor of each member
  2. Fire rating
  3. Critical steel temperature
  4. Surface area
  5. Required DFT
  6. Volume solids of the product
  7. Application losses
  8. Surface preparation and primer
  9. Environment (drying, coats, topcoat)
  10. Inspection requirements

Value engineering levers

  • Use the calculated critical temperature instead of a conservative default.
  • Increase section size where it reduces the section factor of heavily coated members.
  • Compare products – loading tables differ widely.
  • Apply in the shop to reduce losses and site costs.
  • Use boards or sprays where long ratings make coatings uneconomic.

FAQ

How much does intumescent coating cost per m²?

It depends on the DFT, which depends on the member and rating – the same product can cost several times more on a light beam than on a heavy column. Use the estimator with your rates or send the member schedule.

プロジェクトの膜厚とコストが必要ですか?部材リストと耐火性能をお送りください – 当社エンジニアが耐火被覆の提案を作成します。
提案を依頼

Preliminary calculations are provided for estimation purposes only. Final coating thickness and fire protection system selection must be verified against the approved product documentation, applicable project requirements and relevant engineering assessments.