Design and build (EPC) for steel buildings

Design and build (EPC) for steel buildings: one contract covering design, fabrication, shipping and erection, with World Steel coordinating local partners.

Mis à jour 3 min de lecture Voir dans le modèle 3D →

Diagram of the design and build process from concept through handover
Design and build puts design, supply and construction under one contract.

What the service covers

Under a design and build (or EPC) contract, one party takes responsibility for designing, supplying and constructing the building. For steel buildings World Steel offers this through its general contracting solution, with licensed local partners for civil and site works where the project requires them. The stages are:

  1. Brief and concept: user requirements, site constraints, budget and programme.
  2. Design: architectural layout, structure, foundations interface and envelope; permit drawings with local designers as needed.
  3. Procurement: steel from WSC's plant, plus doors, panels, cranes and services from qualified suppliers.
  4. Fabrication and shipment in erection sequence.
  5. Construction: foundations and slab (by partners), steel erection, envelope and accessories.
  6. Testing, handover, as-built documents and warranty.
Design and build process
Design, procurement and construction overlap to shorten the programme.

Inputs needed from the client

  • Site, land title and survey, geotechnical report.
  • Functional brief: use, areas, clear heights, cranes, loading docks, offices.
  • Performance requirements: insulation, fire, ventilation, daylight.
  • Budget, target dates and the owner's approval process.
  • Local authority requirements and the owner's preferred local partners, if any.

For supply-only enquiries, the information needed is summarised in how to request a PEB quotation.

Deliverables

  • Design package for permit and construction, coordinated across structure and envelope.
  • Complete PEB kit and bought-in items.
  • Construction to the agreed scope, with programme and progress reporting.
  • Quality dossier, as-built drawings, operation and maintenance information.

The main advantage is a single point of responsibility: design and fabrication are optimised together, interfaces are managed by one team, and design and procurement overlap to shorten the programme. The trade-off is that the owner sets requirements up front and gives up detailed control of design choices.

Quality and compliance

Steel design and fabrication follow the code of the site and WSC's certified fabrication system (ISO 3834-2, EN 1090-2 EXC3, AS/NZS 5131 CC3, IAS AC472, BC1). Civil works, building services and permits follow local law and are delivered with licensed local partners. Market requirements WSC does not hold itself, such as CSA W47.1 in Canada, AISC Certification in the US or SFC in New Zealand, are addressed per project. See market compliance and certification and PEB design and engineering.

Risk and responsibility

Design and build shifts design risk from the owner to the contractor, so the contract must define the owner's requirements clearly: performance specifications, design loads, finishes, allowances for future expansion and any preferred products. Ground conditions, permits, utility connections and site access are common sources of change and should be allocated explicitly. For export projects the split between World Steel and local partners is set out in a responsibility matrix that covers design stamps, civil works, erection, inspections and warranties, so that every interface has an owner. The owner usually appoints an independent engineer or project manager to review design submissions and monitor quality on site. Change control is agreed at the start: any change to the owner's requirements after design approval is priced and scheduled before it is built, which protects both the budget and the programme.

Special buyouts are a frequent source of interface risk in design and build projects. A responsibility matrix agreed at the start avoids gaps:

Typical interface responsibilities for special items
ItemSupplier providesSteel designer provides
Overhead craneWheel loads, classification, clearances, buffer forcesRunway, brackets, frame and bracing design
Large doors (sectional, sliding, hangar)Weights, reactions, header deflection limits, wind ratingFramed opening, header and wind columns
Sandwich panels and cold roomsSpan tables, fixing, fire classificationPurlin and girt spacing, ceiling hanger loads
Fire protection of steelProduct assessments and thickness tablesSection factors, member list, critical temperatures
Rooftop plant and solarWeights, footprint, wind loadsRoof structure and support framing

See doors and framed openings.

Typical schedule

Typical design-and-build programme for a single-storey PEB (indicative)
PhaseTypical duration
Concept and design approvalAbout 2–6 weeks
PermitsDepends on the authority
Fabrication (overlapping foundations)About 4–8 weeks
Shipping (export projects)About 1–7 weeks depending on destination
Erection and envelopeAbout 3–10 weeks

Durations depend on size, permits, site conditions and decisions by the owner; they are typical and confirmed in each proposal.

Normes par région

RégionNormePérimètre
United States AISC 360-22 / MBMA 2018US steel design and metal building systems
Canada CSA S16-19 / CSA S136-16Canadian steel design
Australia / NZ AS 4100:2020 / AS/NZS 5131Australian design and fabrication
Europe EN 1993 / EN 1090-2Eurocode 3 and execution of steel structures
International ISO 3834-2Welding quality requirements

Questions fréquentes

Does WSC offer design and build outside Vietnam?

For selected export projects, with licensed local partners for civil works and permits; scope is agreed per project.

Is design and build faster?

Usually, because design, fabrication and foundations can overlap and one team manages the interfaces.

Who holds the building permit?

The permit is applied for under local rules, normally by the owner or a licensed local designer working with WSC.