第 9 章 / 全 13 章 · Clause 3.1.1 · Section 10 · Table 10.2 · Clause 11.5.9

Architecturally exposed structural steelwork (AESS)

How AS/NZS 5131 Section 10 grades exposed steel into AESS 1–4 and custom, what the specification must state, and the extra fabrication and erection controls.

AESS applies only to members the construction specification designatesFive categories: AESS 1, 2, 3, 4 and AESS C (custom)The 6 m viewing distance separates AESS 2 from AESS 3AESS 2–4 halve the Appendix F straightness toleranceAESS 4 welds are contoured and blended; seams made invisibleHandling, slinging and site repairs are controlled as well as the shop

When Section 10 applies

AS/NZS 5131 defines architecturally exposed structural steelwork as steel that is visible and forms part of the architectural intent of the building (Clause 3.1.1). Section 10 is not triggered by the construction category: it applies only where the construction specification expressly designates members as AESS, and its requirements sit on top of everything else in the Standard. A CC2 shopping centre can contain AESS 4 feature columns, while a CC3 industrial frame may contain none.

For an assessor, the first question is therefore simple: which members are AESS, and in which category? Without that designation the fabricator works to normal structural workmanship, as described in preparation and fabrication and welding. Each step up the AESS scale adds grinding, filling, handling care and inspection time, so designers are well advised to designate only the surfaces that are actually seen.

The five AESS categories

Clause 10.2 and the AESS matrix in Table 10.2 describe each category by a set of characteristics. The matrix is cumulative: a higher category inherits the characteristics of the lower ones and adds its own. The summary below is written in our words; refer to Table 10.2 for the full matrix.

AESS categories at a glance (summary of Clause 10.2 and Table 10.2)
CategoryTypical useViewing distanceCharacteristic finish
AESS 1 – BasicExposed members needing better-than-normal workmanshipNot definedAt least Sa 2 cleaning, softened edges, continuous weld appearance, spatter removed, standard bolts
AESS 2 – FeatureFeature elements seen from a distanceMore than 6 mAdds tighter fabrication tolerances, hidden fabrication marks, uniform smooth welds
AESS 3 – FeatureFeature elements close to the viewerLess than 6 mAdds removal of mill marks, ground butt and plug welds, aligned abutting sections, hollow-section seams turned away from view
AESS 4 – ShowcaseDominant elements where form is the featureClose viewAdds contoured and blended welds, filled and sanded surfaces, invisible seams, minimised weld show-through
AESS C – CustomProject-specific requirementsAs specifiedCharacteristics chosen individually in the construction specification

The 6 m viewing distance is the practical boundary between AESS 2 and AESS 3. It is a useful prompt for the designer: a roof truss 9 m overhead seldom justifies AESS 3 finishing.

What the construction specification must state

Clause 10.3 places the obligation on the designer to set out AESS requirements in the construction specification (see Appendix B). Machined or locally abraded surfaces must also be identified on the shop and erection drawings. In addition the specification should identify:

  • where one surface treatment changes to another on a member – the transition line or plane;
  • tack welds, temporary braces and fabrication fixtures, and how they are treated;
  • any fabrication or erection tolerances tighter than those in Appendix F;
  • every architecturally sensitive connection detail;
  • the specific requirements of any AESS C element;
  • whether a visual sample or first-off component is required for acceptance before production.

For an offshore fabricator these points must be settled during detailing, before material is cut. Missing information should be raised as a formal request for information and the answer recorded on the shop drawings, so that the factory, the client's inspector and the erector all work to the same standard of finish. See also specification and documentation.

Additional fabrication requirements

Clause 10.4 lists the extra shop controls. The most significant, in summary:

  • Handling: special care to avoid marks and distortion; nylon slings, or chains or wire rope with softeners; soft tie-downs on loads; minimal damage to coatings.
  • Temporary work: tack welds ground smooth; blemishes left by removed braces or fixtures repaired.
  • Geometry: for AESS 2, 3 and 4 the straightness tolerance is half the Appendix F value (Clause 10.4(g)); AESS 3 and 4 require matched abutting cross-sections and uniform gaps or uniform contact at copes, mitres and butt cuts.
  • Welds: spatter, slivers and surface discontinuities removed in every category, with weld preparation grade P3 (Clause 9.8.4); in corrosive environments all joints seal welded.
  • Surfaces: sharp edges from flame cutting, shearing or grinding softened; blast cleaning to at least Sa 2 to AS 1627.4 unless specified otherwise.
Selected finish thresholds by category (summary of Clause 10.4)
CriterionAESS 1AESS 2AESS 3AESS 4
Weld appearanceSmooth, uniformSmooth, uniformSmooth, uniformContoured and blended
Butt and plug weld projectionUp to 2 mmUp to 2 mmGround smoothGround smooth
Straightness toleranceAppendix FHalf Appendix FHalf Appendix FHalf Appendix F
Hollow-section seamAs producedAs producedOriented away from viewTreated so not apparent
Weld show-throughAcceptableAcceptableAcceptableMinimised

Coating requirements follow the normal provisions of Section 9, described in corrosion protection; for AESS the surface preparation and any filler must be compatible with the specified paint or galvanized system.

Visual samples and first-off approval

Table 10.2 treats visual samples as optional in every category; when used, the construction specification chooses the form: a 3D rendering, a physical sample, a first-off inspection, or a scaled or full-scale mock-up. For a project fabricated overseas, an agreed first-off piece is the most reliable way to turn words such as "smooth" and "blended" into an objective acceptance standard. The approved piece – or detailed photographs and measurements of it – then becomes the reference for the rest of the production run and for the pre-shipment inspection.

A first-off approval works best as a hold point in the inspection and test plan, with the client's representative attending in person or by live video, and the outcome recorded in English in the project quality records.

Additional erection requirements

Clause 10.5 – and Clause 11.5.9 in the erection section – carry AESS through to site. The erection must be planned so the architectural appearance survives unloading, handling and lifting. The main points:

  • slings of nylon strap, or chains with softeners; care to limit coating damage;
  • marks from temporary braces or fixtures repaired, and tack welds ground smooth;
  • unwanted holes ground and filled, then finished to the same standard as the shop work;
  • backing bars for site welds removed, the area ground smooth and the coating repaired in accordance with Clause 9.12;
  • bolt heads on the same side within a connection and consistent from one connection to the next;
  • Appendix F erection tolerances, unless the specification sets tighter values.

Because erection is normally carried out by the client's erector, the fabricator's contribution is protective packing, clear piece marks that do not remain visible on finished faces, and erection drawings that flag AESS members. See erection and site work.

審査員チェックリスト

AS/NZS 5131 のこの部分について、技術者、施工者、監査員が CC3 製作会社で確認すべき事項と、求めるべきエビデンス。

条項 · CC確認事項エビデンス
10.1, 10.3 CC1–CC4AESS members and their category are identified for every exposed element before detailing starts.Construction specification, AESS member schedule, marked-up drawings
10.3 CC1–CC4Transition lines, machined or abraded surfaces and architecturally sensitive connections are shown on the drawings.Shop and erection drawings, RFI register
10.3, Table 10.2 CC1–CC4Where specified, the visual sample or first-off piece was accepted before series production.Visual sample or first-off inspection record, photographs, sign-off
10.4(a)–(c) CC1–CC4Handling, lifting and tie-down methods use soft slings or protected chains and limit coating damage.Handling procedure, sling register, packing instructions
10.4(g) CC1–CC4Straightness of AESS 2–4 members is checked against half the Appendix F value.Dimensional inspection reports
10.4(j)–(m) CC1–CC4Weld finish, spatter removal and weld projection meet the category requirements.Visual weld inspection records, ITP sign-offs
10.4(p), (q) CC1–CC4Surface cleaning reaches at least Sa 2 and hollow-section seams are treated to category.Blast cleaning inspection record, seam orientation check
10.5 CC1–CC4Site handling, bolt orientation, removal of backing bars and coating repairs are covered in the erection method.Erection drawings, erector's WMS, site inspection records

当社工場では

World Steel での適用方法

01AESS identified at detailingWorld Steel applies the AESS category from the construction specification to the Tekla model and shop drawings, and raises requests for information where categories or sensitive details are unclear.
02First-off as a hold pointWhere a visual sample or first-off inspection is specified, World Steel's project ITP treats it as a hold point open to the client's inspector in person or by video.
03Finish in the factoryWelding, abrasive blast cleaning and airless spray painting are carried out in World Steel's factory, so weld dressing and surface preparation for AESS members are inspected before coating.
04Protected export packingWorld Steel packs AESS members for export by erection sequence with protection against marking, and records their condition at the pre-shipment inspection.

よくある質問

Does a CC3 project automatically require AESS?

No. The construction category and the AESS category are independent. Section 10 applies only to members the construction specification designates as AESS, whatever the construction category of the structure.

What is the difference between AESS 2 and AESS 3?

Mainly viewing distance and finish. AESS 2 suits feature elements seen from more than about 6 m; AESS 3 is for elements seen closer, and adds requirements such as removing mill marks, grinding butt and plug welds smooth and turning hollow-section seams away from view.

Are AESS tolerances tighter than normal?

Yes. For AESS 2, 3 and 4 the as-fabricated straightness tolerance is half the Appendix F value (Clause 10.4(g)), and AESS 3 and 4 require matched cross-sections and uniform joint gaps. The specification may set further tightened values under Clause 10.3.

Who repairs damage to AESS on site?

Clause 10.5 requires site repairs – filled holes, removed backing bars, coating touch-up – to match the original shop finish. The work is normally done by the erector under its method statement; the fabricator supplies the coating details and repair procedure.