- Bolt group pre-assembled in the shop
- Steel or plywood top templates
- Bottom ring plate holds spacing
- Sleeves for adjustment
- Levelling nuts and plate washers
- Tagged by grid line and foundation
Why cages
Most site problems with steel erection start at the foundation: anchor bolts out of position, rotated or set at the wrong projection. A cage holds the whole bolt group – with a template at the top and a ring plate at the bottom – so it is placed, levelled and tied to the reinforcement as one piece.
What we supply
- Anchor bolts to F1554, AS 1111 or ISO 898-1
- Top template plate drilled from the column base plate drawing
- Bottom ring or spacer plate, tack-welded where permitted
- Plastic or steel sleeves for ± adjustment
- Levelling nuts, plate washers, thread protection
- Tag with foundation mark and grid
Setting
- Check the template against grid lines and level before the pour
- Tie the cage to the reinforcement – not to the formwork
- Protect threads; remove templates after the concrete has set
- Survey bolt positions before steel erection
Standards and requirements by market
Codes World Steel designs, fabricates and documents this product to – and the key geometric and load requirements in each market.
United States
- AISC 303Code of Standard Practice – anchor rod tolerances
- ACI 117Tolerances for concrete
- Position tolerance
- per AISC 303 §7.5
Australia / NZ
- AS/NZS 5131 WSC certifiedHolding-down bolt tolerances
Summary for orientation only – the project specification, the adopted code edition and the authority having jurisdiction govern.
Finishes
| Finish | Standards / notes |
|---|---|
| Bolts | Hot-dip galvanized |
| Templates | Primed or plain |







